Led a fixed-scope infrastructure build from zero: audited the production factory, researched and tested the hardware, and coordinated the engineering team for the mining setup and purpose-built software. Designed and built a first mining datacenter at scale, seeding a lasting collaboration with a regional operator. Delivered as a phased waterfall program. Partner and location details altered.
REDACTED All cases are reconstructed and sanitized. The documents are freshly authored, not the client's originals: sensitive data has been altered and the most delicate parts removed for confidentiality. Client names, buyers, individuals and exact figures are redacted or changed. The structure, governance, workflow and results reflect real work.
Delivery board
The programme mapped across eleven board pages, from current state to measured outcome. The stage-gate governance page is the centre of gravity.
Programme documents
The document set that ran the programme, from mandate to benefits realization. Open any document to read it in full.
Owner: Project lead · Method: Waterfall · Status: Approved at initiation · Classification: Internal (sanitized)
Sanitized. Partner, location and figures altered.
1. Purpose
Authorize the design and construction of a first cryptocurrency mining datacenter, from zero, and the purpose-built software to operate it. This charter sets the mandate, scope and the phased plan by which it was delivered.
2. Rationale
The opportunity was to build early mining infrastructure at a time when doing so was new territory: the hardware was immature, the operating software largely had to be built, and there was no established playbook. The mandate was to turn that into a working facility, on a defined scope and budget, with the diligence that a capital build demands.